Time Limits for Arbitration Under Section 29A 

Share & spread the love

The Arbitration and Conciliation Act, 1996 was enacted to promote arbitration as an efficient and time-bound alternative to court litigation. However, over the years, arbitration proceedings in India began to suffer from delays similar to traditional civil suits. To address this concern, Parliament introduced Section 29A through the Arbitration and Conciliation (Amendment) Act, 2015. The provision sought to impose statutory timelines for the completion of arbitral proceedings and the making of arbitral awards.

Section 29A has since undergone further modification through the Arbitration and Conciliation (Amendment) Act, 2019. Together, these amendments reflect a legislative attempt to balance two competing objectives: procedural efficiency and fairness in arbitration. This article provides a detailed and structured analysis of time limits for arbitration under Section 29A, tracing its evolution, scope, judicial interpretation, and practical implications.

Legislative Background of Section 29A of Arbitration and Conciliation Act, 1996

Position Prior to the 2015 Amendment

Before 2015, the Arbitration and Conciliation Act, 1996 did not prescribe any statutory time limit for the conclusion of arbitral proceedings. The duration of arbitration was largely dependent on party conduct, procedural complexity, and tribunal efficiency. While flexibility was considered an advantage, the absence of timelines often resulted in prolonged proceedings.

This delay undermined confidence in arbitration as a speedy dispute resolution mechanism and prompted calls for legislative reform.

Introduction of Section 29A in 2015

Section 29A was inserted by the 2015 Amendment with effect from 23 October 2015. The provision introduced a mandatory time limit of 12 months for making an arbitral award, calculated from the date on which the arbitral tribunal “entered upon the reference”.

The key objectives behind this amendment were:

  • To reduce procedural delays in arbitration
  • To introduce accountability for arbitrators and parties
  • To align Indian arbitration law with global best practices

However, the use of the phrase “entered upon the reference” soon became a subject of interpretative difficulty.

Structure of Section 29A of Arbitration and Conciliation Act, 1996

Section 29A is a self-contained provision dealing with timelines, extensions, consequences of delay, and court intervention. Its key sub-sections operate together and must be read harmoniously.

Section 29A(1): Statutory Time Limit

Under the current framework, Section 29A(1) mandates that the arbitral award shall be made within 12 months from the date of completion of pleadings.

This position was introduced by the 2019 Amendment and marked a shift away from the earlier reference-based trigger.

Section 29A(3): Extension by Consent of Parties

Section 29A(3) allows the parties to mutually extend the time period by a further six months. This extension does not require court intervention and is intended to preserve party autonomy.

Once this additional six-month period expires, the total available time becomes 18 months.

Section 29A(4): Extension by Court

If the award is not made within the period specified under sub-sections (1) and (3), either party may apply to the competent court for extension of the arbitral tribunal’s mandate.

The provision clarifies that:

  • The court may extend the mandate either before or after the expiry of the specified period
  • The mandate of the tribunal terminates unless such extension is granted

Section 29A(5) and (8): Safeguards and Costs

To prevent misuse, Section 29A(5) requires the applicant to show sufficient cause for the delay. The court may also impose terms and conditions.

Section 29A(8) empowers the court to impose costs on parties responsible for delay, reinforcing procedural discipline.

The 2019 Amendment and the Shift to Completion of Pleadings

One of the most significant changes introduced by the 2019 Amendment was the replacement of the phrase “entered upon the reference” with “date of completion of pleadings”.

This change was aimed at addressing practical difficulties, as tribunals were often constituted but unable to proceed due to delayed pleadings. By linking timelines to the completion of pleadings, the legislature ensured that the clock starts only when the arbitration is procedurally ready for adjudication.

This amendment has been widely regarded as a pragmatic and arbitration-friendly reform.

Applicability of Section 29A to Pre-2015 Arbitrations

A recurring question before Indian courts has been whether Section 29A applies to arbitrations that commenced prior to the 2015 Amendment.

Judicial Position on Commencement of Arbitration

Courts have consistently held that commencement of arbitration under Section 21 of the Act is the determinative factor for assessing the applicability of Section 29A.

In M/s Chinar Steel Industries v. IRCON International Ltd., the Delhi High Court clarified that:

  • The date of invocation of arbitration is decisive
  • The date on which the arbitral tribunal was constituted or entered reference is irrelevant
  • Arbitrations commenced prior to 23 October 2015 are not governed by Section 29A

This interpretation ensures certainty and avoids retrospective application of statutory timelines.

Extension of Time After Expiry of Mandate: Judicial Divergence

A major area of controversy under Section 29A relates to whether courts can extend the mandate of an arbitral tribunal after the expiry of the statutory period.

Liberal Interpretation by Certain High Courts

The Delhi High Court, Bombay High Court, and Madhya Pradesh High Court have adopted a purposive approach. These courts have emphasised:

  • The stage of arbitration proceedings
  • Whether delay is attributable to parties or external factors
  • The need to prevent wastage of time and resources

In cases where proceedings were at an advanced stage, courts have extended the mandate even after expiry, holding that a rigid interpretation would defeat the objective of dispute resolution.

Strict Interpretation by the Calcutta High Court

In Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., the Calcutta High Court took a stricter view. The court held that once the statutory period expires without an extension application, the mandate of the tribunal automatically terminates.

The court relied on legislative intent and the conscious use of the word “terminate” instead of “suspend”.

This judgment has led to uncertainty, particularly since Special Leave Petitions against similar rulings are pending before the Supreme Court.

Role of Courts Under Section 29A

Section 29A reflects a calibrated degree of judicial intervention. Courts are not expected to supervise arbitration proceedings but are empowered to ensure timely completion.

While exercising powers under Section 29A, courts generally consider:

  • Cause of delay
  • Conduct of parties
  • Progress of proceedings
  • Complexity of disputes

Courts also retain the power to substitute arbitrators where delay is attributable to the tribunal.

Conclusion

Section 29A represents a significant legislative intervention aimed at ensuring time-bound arbitration in India. Through the 2015 and 2019 amendments, Parliament has sought to strike a balance between efficiency, fairness, and party autonomy.

Judicial decisions have clarified key aspects such as the applicability of Section 29A to post-2015 arbitrations, the relevance of commencement under Section 21, and the scope of court-granted extensions. However, divergent interpretations on post-expiry extensions continue to create uncertainty.


Attention all law students and lawyers!

Are you tired of missing out on internship, job opportunities and law notes?

Well, fear no more! With 2+ lakhs students already on board, you don't want to be left behind. Be a part of the biggest legal community around!

Join our WhatsApp Groups (Click Here) and Telegram Channel (Click Here) and get instant notifications.

Aishwarya Agrawal
Aishwarya Agrawal

Aishwarya is a gold medalist from Hidayatullah National Law University (2015-2020). She has worked at prestigious organisations, including Shardul Amarchand Mangaldas and the Office of Kapil Sibal.

Articles: 5672

Leave a Reply

Your email address will not be published. Required fields are marked *

NALSAR IICA LLM 2026