Shripati Lakhu Mane v The Member Secretary, Maharashtra Water Supply and Sewerage Board

The case of Shripati Lakhu Mane v. The Member Secretary, Maharashtra Water Supply and Sewerage Board revolves around the concept of abandonment under contract law. The key legal issue in this case was whether a party to a contract can be said to have abandoned the contract when they refuse to perform their obligations, or if such refusal constitutes a breach of contract instead. The Supreme Court, in its judgement, clarified that refusal to perform obligations amounts to a breach of contract and not abandonment.
The judgement helps in distinguishing between “abandonment” and “breach” in the context of a contractual obligation.
Facts of Shripati Lakhu Mane v The Member Secretary, Maharashtra Water Supply and Sewerage Board
The appellant, Shripati Lakhu Mane, was a registered contractor who was issued a work order on 3rd July 1986 by the Maharashtra Water Supply and Sewerage Board for a water supply scheme in Ratnagiri District. The stipulated time for completing the work was 30 months.
However, on 28th July 1986, the respondents (the Maharashtra Water Supply and Sewerage Board) informed the appellant to keep the work order in abeyance. Later, on 17th December 1986, they instructed the appellant to resume work.
The appellant raised an issue about the non-availability of the specified pipes and requested revised rates for using different dimensions of pipes. Before resolving this issue, on 2nd March 1987, the respondents instructed the appellant to halt the pipeline work and start work at a different location. Subsequently, modifications were made to the scheme, and the appellant contended that the work could not be completed due to lack of funds and delays in sanctioning modified rates.
Despite these challenges, the respondents imposed a penalty of Rs. 10 per day for the delay and ordered the appellant to resume work. This led to a dispute, and the appellant filed a suit in the Trial Court for the recovery of Rs. 51,35,289.
The Trial Court partly decreed the appellant’s suit, awarding Rs. 24,97,077 along with interest. The respondents, however, appealed to the High Court, which reduced the decree amount to Rs. 7,19,412, reasoning that the appellant had abandoned the contract.
The appellant then appealed to the Supreme Court, challenging the High Court’s finding that he had abandoned the contract.
Issues Involved
The central issue before the Supreme Court was whether the appellant had abandoned the contract. Specifically, the Court was tasked with determining if the refusal to perform the contractual obligations by the appellant amounted to abandonment of the contract or a breach of the contract.
Observations by the Supreme Court in Shripati Lakhu Mane v The Member Secretary, Maharashtra Water Supply and Sewerage Board
The Supreme Court referred to Section 67 of the Indian Contract Act, 1872 (ICA), which states that if the promisee neglects or refuses to provide the promisor with reasonable facilities for the performance of the contract, the promisor is excused for any non-performance resulting from such neglect or refusal.
The Court explained that abandonment of a contract refers to a situation where a party gives up its rights under the contract, leading to the possibility of a waiver by the other party. However, abandonment does not apply to obligations.
In the case at hand, the Court stated that the appellant’s refusal to perform his obligations unless the other party (the respondents) fulfilled their reciprocal promises could not be construed as abandonment. Instead, it should be considered as a breach of contract.
The Court further emphasised that when there is a material alteration to the original contract (such as delays or changes in the agreed terms), a party may refuse to perform the contract. However, such refusal does not amount to abandonment of the contract. Abandonment is a right, not an obligation.
The Court observed that refusal to fulfill the obligations under a contract constitutes a breach. In this case, the appellant’s refusal to continue with the work unless the respondents met their obligations could be considered a breach, but not abandonment.
The Court also clarified that when one party refuses to perform their obligations under a contract, the other party has the option to either:
- Sue for breach of contract, or
- Rescind the contract and claim a quantum meruit (payment for the work already performed).
The Supreme Court concluded that the High Court had made an error in reducing the amount awarded to the appellant by concluding that he had abandoned the contract.
Conclusion
The Supreme Court’s decision in Shripati Lakhu Mane v. The Member Secretary, Maharashtra Water Supply and Sewerage Board affirmed that refusal to perform a contractual obligation does not amount to abandonment. Instead, such refusal is deemed a breach of contract.
The judgement also made it clear that abandonment pertains to rights and not obligations. Therefore, a contractor or any party to a contract may refuse to continue performing their obligations unless the other party fulfills their reciprocal promises. However, this refusal must be viewed as a breach of contract, not as abandonment.
Thus, the High Court’s decision to reduce the amount on the grounds of abandonment was overturned by the Supreme Court, which held that the appellant had not abandoned the contract, but had simply refused to perform due to non-fulfillment of the other party’s obligations.
Attention all law students and lawyers!
Are you tired of missing out on internship, job opportunities and law notes?
Well, fear no more! With 2+ lakhs students already on board, you don't want to be left behind. Be a part of the biggest legal community around!
Join our WhatsApp Groups (Click Here) and Telegram Channel (Click Here) and get instant notifications.








