Hindustan Construction Company Limited & Anr. v. Union of India & Ors.

The decision of the Supreme Court in Hindustan Construction Company Limited & Anr. v. Union of India & Ors. is a significant judgement in Indian arbitration law. The case examined the constitutional validity of Section 87 of the Arbitration and Conciliation Act, 1996, inserted by the Arbitration and Conciliation (Amendment) Act, 2019. The judgement dealt with the persistent problem of automatic stay on arbitral awards, an issue that the 2015 amendment had sought to remove.
The Court also examined the broader implications of Section 87 on arbitral enforcement, contractual certainty, and the interaction between arbitration law and the Insolvency and Bankruptcy Code, 2016 (IBC). The judgement reaffirmed India’s pro-arbitration approach and clarified that legislative changes should support, and not frustrate, the enforcement of arbitral awards.
Background and Legal Context
The Arbitration and Conciliation Act, 1996 was enacted with the objective of reducing judicial intervention and ensuring speedy resolution of disputes. However, judicial interpretation of Section 36 of the unamended Act resulted in a situation where arbitral awards were automatically stayed once an application was filed under Section 34 to set aside the award.
This created severe delays for award holders, who could not enforce awards even when there was no specific order of stay from the court. The problem was corrected through the Arbitration and Conciliation (Amendment) Act, 2015, which made it clear that filing a Section 34 application would not result in an automatic stay and that a separate stay application would need to be filed.
In BCCI v. Kochi Cricket Pvt. Ltd. (2018), the Supreme Court further clarified that this removal of automatic stay would apply even to pending court proceedings initiated after 23 October 2015. This judgement strengthened enforcement of arbitral awards and improved confidence in arbitration as an effective dispute resolution mechanism.
However, the Arbitration and Conciliation (Amendment) Act, 2019 inserted Section 87 and repealed Section 26 of the 2015 Amendment Act. This legislative move attempted to restore the pre-2015 position by reviving ambiguity regarding the applicability of the 2015 amendment, particularly in relation to automatic stay.
Facts of Hindustan Construction Company Limited & Anr. v. Union of India & Ors. Case
Hindustan Construction Company Limited (HCC) is a well-known engineering and infrastructure company engaged in executing large-scale public infrastructure projects. It carried out projects for government bodies such as NHAI, NHPC, NTPC, and IRCON International.
Due to design changes, execution delays, and cost overruns, disputes arose between HCC and these government agencies. These disputes were resolved through arbitration, and several arbitral awards were passed in favour of HCC.
The government agencies, as award debtors, challenged these awards under Sections 34 and 37 of the Arbitration Act. Following the insertion of Section 87, these challenges led to compulsory and automatic stays on the execution of arbitral awards. As a result, HCC was unable to enforce awards despite having succeeded in arbitration.
The situation worsened because government bodies were excluded from the definition of “corporate person” under the IBC, while HCC, as a private entity, was not. This meant that HCC could not initiate insolvency proceedings against government bodies for non-payment of awards, but its own creditors could initiate insolvency proceedings against HCC.
Thus, while HCC’s legitimate dues were blocked due to automatic stay, it faced insolvency pressure from operational creditors. This imbalance prompted HCC to approach the Supreme Court.
Issues for Consideration
The Supreme Court in Hindustan Construction Company Limited & Anr. v. Union of India & Ors. considered the following key issues:
- Whether Section 87 of the Arbitration and Conciliation Act, 1996 is constitutionally valid.
- Whether the 2019 amendment, by inserting Section 87 and repealing Section 26, nullified or encroached upon the judgement in BCCI v. Kochi Cricket Pvt. Ltd.
- Whether Section 87 led to arbitrary and unreasonable results when read along with the provisions of the IBC.
Arguments Advanced by the Petitioners
The petitioners contended that Section 87 effectively revived the automatic stay regime that existed prior to the 2015 amendment, thereby undoing a crucial reform in arbitration law.
It was argued that the original Act did not provide for automatic stay, and such a consequence only arose due to judicial interpretation. The 2015 amendment corrected this position by making enforcement of awards the norm rather than the exception.
The petitioners pointed out that the Government relied upon the Justice B.N. Srikrishna Committee Report to justify the insertion of Section 87. However, even before the 2019 amendment, the Supreme Court in BCCI v. Kochi Cricket Pvt. Ltd. had already resolved the ambiguity regarding the applicability of the 2015 amendment and had communicated its concerns to the legislature.
It was also argued that Section 87 amounted to a legislative attempt to override a binding judicial precedent, which went against the principles of separation of powers.
Further, the petitioners contended that Section 87 violated Articles 14, 19(1)(g), 21, and 300A of the Constitution of India. The provision was arbitrary, unreasonable, and resulted in deprivation of property without authority of law.
In addition, the petitioners highlighted the inconsistency between civil decrees and arbitral awards. Unlike civil appeals, where money decrees are not automatically stayed, arbitral awards were subjected to automatic stay merely due to the filing of a challenge.
Arguments Advanced by the Respondents
The Union of India defended the 2019 amendment by stating that the interpretation of Section 26 in BCCI v. Kochi Cricket Pvt. Ltd. was declaratory in nature. It was argued that Parliament was competent to clarify its original intent through legislative amendment.
The respondents contended that Section 87 was merely clarificatory and did not amount to overruling or invalidating the BCCI judgement. According to them, the amendment restored the intended prospective application of the 2015 amendment.
On the issue of arbitrariness, it was argued that fixing 23 October 2015 as the cut-off date was a policy decision and courts should not interfere unless it was manifestly discriminatory.
Regarding the challenge to the IBC, the respondents argued that Article 32 proceedings could not be used to convert writ jurisdiction into a recovery mechanism.
Reasoning and Findings of the Supreme Court in Hindustan Construction Company Limited & Anr. v. Union of India & Ors.
The Supreme Court agreed with the petitioners and held that Section 87 reintroduced the very mischief that the 2015 amendment sought to remove.
The Court observed that the original Act did not contemplate any automatic stay on enforcement of arbitral awards. The automatic stay arose because of judicial interpretation, which was later corrected legislatively in 2015.
It was noted that the insertion of Section 87 was based solely on the recommendations of the Srikrishna Committee to remove ambiguity. However, such ambiguity had already been clarified conclusively in BCCI v. Kochi Cricket Pvt. Ltd.
The Court held that the legislature, by ignoring the judicial declaration in BCCI, enacted a provision that was manifestly arbitrary and contrary to the object of the Act. The amendment failed the test of reasonable classification under Article 14.
The Court also examined the impact of Section 87 when read with the IBC. It found that the provision resulted in absurd outcomes where award holders were prevented from enforcing awards but were themselves exposed to insolvency proceedings. This imbalance was found to be destructive to public interest, especially in infrastructure and construction sectors.
The Supreme Court reiterated that insolvency law is not meant to be a substitute for recovery proceedings and relied upon its earlier ruling in Pioneer Urban Land and Infrastructure Ltd. v. Union of India to reinforce this principle.
Hindustan Construction Company Limited & Anr. v. Union of India & Ors. Judgement
The Supreme Court in Hindustan Construction Company Limited & Anr. v. Union of India & Ors. struck down Section 87 of the Arbitration and Conciliation Act, 1996 as unconstitutional. It held that the provision was arbitrary, unreasonable, and contrary to the object of the 2015 amendment.
The Court restored the legal position laid down in BCCI v. Kochi Cricket Pvt. Ltd. and clarified that filing a petition under Section 34 does not result in an automatic stay on enforcement of arbitral awards, irrespective of when the arbitral proceedings commenced.
Conclusion
The judgement in Hindustan Construction Company Limited & Anr. v. Union of India & Ors. reaffirmed the Supreme Court’s commitment to strengthening arbitration as a reliable dispute resolution mechanism in India. By striking down Section 87, the Court ensured that award holders are not deprived of the fruits of arbitration due to prolonged litigation tactics.
The decision restored certainty in arbitral enforcement, protected commercial confidence, and prevented misuse of insolvency law against genuine award holders. It stands as a crucial precedent in maintaining fairness, efficiency, and balance between award debtors and award creditors within the framework of Indian arbitration law.
Attention all law students and lawyers!
Are you tired of missing out on internship, job opportunities and law notes?
Well, fear no more! With 2+ lakhs students already on board, you don't want to be left behind. Be a part of the biggest legal community around!
Join our WhatsApp Groups (Click Here) and Telegram Channel (Click Here) and get instant notifications.








